Concrete firm fined £100,000 following university fatality

A concrete-products manufacturer has been ordered to pay £240,000 in fines and costs following the death of a carpenter during construction of a new accommodation building at Bath University.

Creagh Concrete Products Ltd was contracted to design, manage and build the concrete framing for 380 new student rooms at the University’s Claverton Down Campus.

The company sub-contracted Philip Hames to work as a carpenter and on 1 November 2007 he and a colleague were attempting to install wooden shuttering on the first floor of the building.€

[vc_row][vc_column width="2/3"][vc_column_text]

The Safety Conversation Podcast: Listen now!

The Safety Conversation with SHP (previously the Safety and Health Podcast) aims to bring you the latest news, insights and legislation updates in the form of interviews, discussions and panel debates from leading figures within the profession.Find us on Apple Podcasts, Spotify and Google Podcasts, subscribe and join the conversation today![/vc_column_text][vc_empty_space height="15px"][vc_btn title="Listen here!" color="success" link="url:https%3A%2F%2Fwww.shponline.co.uk%2Fthe-safety-and-health-podcast%2F|target:_blank"][/vc_column][vc_column width="1/3"][vc_single_image image="91215" img_size="medium"][/vc_column][/vc_row]
Concrete firm fined £100,000 following university fatality A concrete product manufacturer has been ordered to pay £240,000 in fines and costs following the death of a carpenter during construction of a new accommodation building at Bath University.
SHP - Health and Safety News, Legislation, PPE, CPD and Resources

Related Topics

Comments
  • Bob

    Again no refernece o the requirements of CDM to assess the risk at design stage, and thereafter to adopt adequate control of said risk.

    Where are the appointed people whom determine the design risk?

    What of the CDMC requirement to ensure design risk is mitigated by adoption of a proven SSoW?

    Who designed the propping detail, and where is the reference to the safe sequence of work? Any propping detail generally requires adequate head restraint, this is not rocket science.

    Truely shocked.