SHP Online is part of the Informa Markets Division of Informa PLC

SHP Online is operated by a business or businesses owned by Informa PLC and all copyright resides with them. Informa PLC's registered office is 5 Howick Place, London SW1P 1WG. Registered in England and Wales. Number 8860726.

August 31, 2018

Get the SHP newsletter

Daily health and safety news, job alerts and resources

Crossrail

Crossrail delay: More time needed to ensure ‘safe and reliable railway’

London’s Crossrail is set to miss its December opening date by ninth months.

Elizabeth_lineServices on London’s Crossrail will not begin until autumn next year, a spokesperson for the project has announced.

The latest addition to the underground network, which will be known as the Elizabeth Line once opened, had been due for completion this December.

However, Crossrail Limited has said that more time is needed to complete “final infrastructure and extensive testing” to ensure a “safe and reliable railway” is delivered for customers “from day one of passenger service”.

Services are already running on part of the line, temporarily dubbed TFL Rail, but the central section between Paddington and Abbey Wood will now not open until autumn 2019.

The construction of the project is drawing to a close with the completion of the remaining mechanical, electrical and communications systems along with architectural fit-out in the new central section stations.

The remaining rail infrastructure works are due to be completed this year. This ranges from removal of temporary services to completing the remaining installation of the permanent lighting and drainage pumps in the tunnels.

Simon Wright, Crossrail Chief Executive, said: “The Elizabeth line is one of the most complex and challenging infrastructure projects ever undertaken in the UK and is now in its final stages.

“We have made huge progress with the delivery of this incredible project but we need further time to complete the testing of the new railway.

“We are working around the clock with our supply chain and Transport for London to complete and commission the Elizabeth line.”

The original programme for testing is said to have been compressed by more time being needed by contractors to complete fit-out activity in the tunnels and the development of railway systems software.

Railway systems cover the integrated systems and associated software that required to operate the railway including rolling stock, signalling, tunnel ventilation, communications and power.

When it is fully opened, trains will run from Reading and Heathrow in the west through 13 miles of new tunnels to Shenfield and Abbey Wood in the east.

Updated Monday 3 September.

TfL apologises after Jubilee Line tube train filmed moving with doors open

[vc_row][vc_column width="2/3"][vc_column_text]

Driving for Better Safety - Free eBook download

This eBook will guide you through some of the key understandings you need to be able to manage driver safety effectively and, at the end, provide a series of free resources you can access to help you ensure your own driver safety management system is robust, legally compliant and in line with industry-accepted good practice.Download this eBook from Driving for Better Business and SHP to cover:
  • Why do we need to manage driver safety?
  • Duty of care – a shared responsibility;
  • Setting the rules with a driving for work policy;
  • Managing driver safety;
  • Ensuring safe vehicles;
  • Safe journeys and fitness to drive;
  • Record keeping;
  • Reporting;
  • The business benefits of good practice;
  • Additional resources
[/vc_column_text][vc_empty_space][vc_btn title="Download Now" color="green" size="lg" align="center" link="url:https%3A%2F%2Fwww.shponline.co.uk%2Fresources%2Fgood-practice-in-driver-safety-management%2F"][/vc_column][vc_column width="1/3"][vc_single_image image="85471" img_size="full"][/vc_column][/vc_row]
Crossrail delay: More time needed to ensure ‘safe and reliable railway’ Crossrail Limited has said that more time is needed to complete “final infrastructure and extensive testing” to ensure a “safe and reliable railway” is delivered for customers “from day one of passenger service”.
SHP - Health and Safety News, Legislation, PPE, CPD and Resources

Related Topics

Leave a Comment
Cancel reply

Exit mobile version